U.S. 50 HOV Lanes (Phase 1) - El Dorado Hills to Bass Lake Grade
CIP Project No.
53110
|
|
 |
|
| Project Description:
This project is part of a larger plan to add HOV lanes to US 50 from El Dorado Hills to Shingle Springs being developed jointly by the County and Caltrans. This project includes construction of HOV lanes in the median of US 50 from El Dorado Hills Boulevard/Latrobe Road to the top of the Bass Lake Grade Westbound and the bottom of the Bass Lake Grade eastbound, and extension of the eastbound truck lane from Latrobe Rd to the bottom of the Bass Lake Grade. It includes median widening of Clarksville Road undercrossings and replacement of the El Dorado Hills Boulevard undercrossings including the eastbound off ramp.
|
| View On Microsoft Live Maps™
|
| Click image to view larger |
Click image to view larger |
 |
 |
| U.S. 50 HOV Lanes - El Dorado Hills to Bass Lake Grade (# 53110) |
|
| |
| Project Milestone Schedule |
Estimated Completion Date |
| PA&ED - Project Approval & Environmental Document |
June 2002 |
| PSE - Plans, Specifications & Estimates |
February 2008 |
| Advertise for Construction/Award Contract |
September 2008 |
| Construction Complete |
June 2011 |
|
| Total Estimated Project Cost:
$43,573,431
|
|
| |
| Project Status:
Currently being updated
Last Updated:
02/25/10 |
| |
| Project Contacts: |
| Project Manager: |
Rick Carter |
(530) 621-5900 |
Send Email |
| Deputy Director: |
Matt Smeltzer |
(530) 621-5900 |
Send Email |
|
| |