U.S. 50 HOV Lanes (Phase 2A) - Bass Lake Road to Cameron Park Drive
CIP Project No.
53113
|
|
 |
|
| Project Description:
This is a joint project between the County and Caltrans and part of a larger plan to add HOV lanes to US 50 from El Dorado Hills to Shingle Springs. This project includes the construction of HOV lanes from the Bass Lake Grade to Cameron Park Drive. Project approval and environmental documents have been completed by Caltrans. Caltrans is advancing the design of this project through a cooperative agreement.
|
| View On Microsoft Live Maps™
|
| Click image to view larger |
Click image to view larger |
 |
 |
| U.S. 50 HOV Lanes - Bass Lake Grade to Ponderosa Road (# 53113) |
|
| |
| Project Milestone Schedule |
Estimated Completion Date |
| PA&ED - Project Approval & Environmental Document |
June 2002 |
| PSE - Plans, Specifications & Estimates |
June 2011 |
| Advertise for Construction/Award Contract |
December 2011 |
| Construction Complete |
June 2015 |
|
| Total Estimated Project Cost:
$18,860,174
|
|
| |
| Project Status:
Currently being updated
Last Updated:
08/09/10 |
| |
| Project Contacts: |
| Project Manager: |
Rick Carter |
(530) 621-5900 |
Send Email |
| Deputy Director: |
Matt Smeltzer |
(530) 621-5900 |
Send Email |
|
| |
| Board of Supervisor District: | District 1, Supervisor:   John Knight | | | District 2, Supervisor:   Ray Nutting
|
|