U.S. 50/Missouri Flat Road Interchange Improvements - Phase 1A
CIP Project No.
71317
|
|
 |
|
| Project Description:
The Phase 1A US 50/Missouri Flat Road Interchange project widened Missouri Flat Road from Mother Lode Drive to Prospector's Plaza Drive from two (2) lanes to four (4) lanes, added turn lanes and replaced the existing overcrossing structure at US 50. Intersection improvements/channelization were included at Prospector's Plaza Drive, US 50 eastbound and westbound ramps, Mother Lode Drive and Perks Court intersections. See project 71336 for Phase 1B.
|
| View On Microsoft Live Maps™
|
| Click image to view larger |
Click image to view larger |
 |
 |
| U.S. 50/Missouri Flat Road Interchange Improvements Phase 1A (# 71317) |
U.S. 50/Missouri Flat Road Interchange Phases 1 A/B (Rendering) |
| |
| Project Milestone Schedule |
Estimated Completion Date |
| PA&ED - Project Approval & Environmental Document |
April 2005 |
| PSE - Plans, Specifications & Estimates |
July 2006 |
| Advertise for Construction/Award Contract |
September 2006 |
| Construction Complete |
December 2008 |
|
| Total Estimated Project Cost:
$35,747,691
|
|
| |
| Project Status:
Currently being updated
Last Updated:
08/16/10 |
| |