COUNTY OF EL DORADO DEPARTMENT OF TRANSPORTATION
El Dorado County Seal - Click to return to County Home page
U.S. 50/Camino Area Parallel Capacity/Safety Study
CIP Project No.  71319
DOT Seal
Project Description:   The long-term goal of the Camino Corridor Operational Improvements is to improve access and reduce accidents on U.S. 50. El Dorado County Transportation Commission (EDCTC) is the lead agency on the preparation of the Study and is responsible for identifying access and safety improvement alternatives. Included in the Study parameters is a comprehensive public outreach effort. Funds in 06/07 through 09/10 provide a County contribution to the Study.

View On Microsoft Live Maps™

Click image to view larger Click image to view larger
Location Map Project Photo
U.S. 50/Camino Area Parallel Capacity/Safety Study (# 71319) U.S. 50/Camino Road Intersection
 
Project Milestone Schedule Estimated Completion Date
PA&ED - Project Approval & Environmental Document Beyond Five Years*
PSE - Plans, Specifications & Estimates Beyond Five Years*
Advertise for Construction/Award Contract Beyond Five Years*
Construction Complete Beyond Five Years*
 
Total Estimated Project Cost:   $4,332,441
 
Project Status:   Currently being updated   Last Updated:   01/11/10
 
Project Contacts:
Project Manager: Adam Bane (530) 621-5900 Send Email
Deputy Director: Matt Smeltzer (530) 621-5900 Send Email
 
Board of Supervisor District: District 3, Supervisor:   James R (Jack) Sweeney