| COUNTY OF EL DORADO |
DEPARTMENT OF TRANSPORTATION |
 |
U.S. 50/El Dorado Hills Boulevard Interchange Improvements
CIP Project No.
71323
|
|
 |
|
| Project Description:
Part of larger project to reconstruct the interchange and widen Latrobe Rd/El Dorado Hills Boulevard. Complete reconstruction is being phased to align improvement needs, construction staging within US 50 corridor, and available funding. This final phase constructs new westbound loop off-ramp undercrossing and new westbound diagonal on-ramp, improves on-/off-ramps for eastbound US 50 and widens Latrobe Rd/El Dorado Hills Boulevard to 3 through lanes in each direction; dual left turns at both ramps, Saratoga Way, and Town Center; and 1 merge lane at both loop off-ramps that extends through the signalized intersection. Project includes roadwork and retaining walls, barrier, sidewalks, railings and landscape replacement on the east side of El Dorado Hills Boulevard between Saratoga and Town Center that is environmentally cleared by project 71340 (construction cost +/- $1,000,000, ROW costs +/- $300,000). Design to be coordinated with Mainline Widening (53120), Westbound Auxillary Lane (53115) and Pedestrian Overcrossing (71340). Construction should preceed or be concurrent with the 53120 and 53115 projects.
|
| View On Microsoft Live Maps™
|
| Click image to view larger |
Click image to view larger |
 |
 |
| U.S. 50/El Dorado Hills Boulevard Interchange Improvements (71323) |
U.S. 50/El Dorado Hills Boulevard Interchange Aerial |
| |
| Project Milestone Schedule |
Estimated Completion Date |
| PA&ED - Project Approval & Environmental Document |
April 2000 |
| PSE - Plans, Specifications & Estimates |
January 2016 |
| Advertise for Construction/Award Contract |
May 2019 |
| Construction Complete |
November 2020 |
|
| Total Estimated Project Cost:
$26,010,826
|
|
| |
| Project Status:
Currently being updated
Last Updated:
02/25/10 |
| |
| Project Contacts: |
| Project Manager: |
Rick Carter |
(530) 621-5900 |
Send Email |
| Deputy Director: |
Matt Smeltzer |
(530) 621-5900 |
Send Email |
|
| |
| Board of Supervisor District: | District 2, Supervisor:   Ray Nutting
|
|