COUNTY OF EL DORADO DEPARTMENT OF TRANSPORTATION
El Dorado County Seal - Click to return to County Home page
U.S. 50/Cambridge Road Interchange Improvements - Phase 1
CIP Project No.  71332
DOT Seal
Project Description:   Phase 1 Improvements to Cambridge Road interchange. Phase I project consists of widening the existing EB and WB off-ramps; addition of new WB on-ramp from SB Cambridge Road; reconstruction of the local intersections to provide for additional capacity, both turning and through; and the installation of traffic signals at EB ramp terminal intersection. Also includes preliminary engineering for Phase 2 improvements to Cambridge Interchange (GP149).

View On Microsoft Live Maps™

Click image to view larger Click image to view larger
Location Map Project Photo
U.S. 50/Cambridge Road Interchange Improvements - Phase 1 (71332) U.S. 50/Cambridge Road Interchange Aerial
 
Project Milestone Schedule Estimated Completion Date
PA&ED - Project Approval & Environmental Document Beyond Five Years*
PSE - Plans, Specifications & Estimates Beyond Five Years*
Advertise for Construction/Award Contract Beyond Five Years*
Construction Complete Beyond Five Years*
 
Total Estimated Project Cost:   $10,645,722
 
Project Status:   Currently being updated   Last Updated:   01/06/10
 
Project Contacts:
Project Manager: Rupa Somavarapu (530) 621-5900 Send Email
Deputy Director: Craig McKibbin (530) 621-5900 Send Email
 
Board of Supervisor District: District 1, Supervisor:   John Knight
  District 2, Supervisor:   Ray Nutting