U.S. 50/Ponderosa Rd Interchange - Durock Rd Realignment
CIP Project No.
71338
|
|
 |
|
| Project Description:
This project includes realignment of approximately 1/4 mile of Durock Road to Sunset Lane and signalization of the new intersection. Durock Road will be two through lanes with turn pockets at the intersection and center turn lane. This project is part of a larger project, US 50/Ponderosa Road/South Shingle Road interchange (project 71333). Preliminary engineering shall be performed under the interchange project. Work needs to be coordinated with US 50/Ponderosa Road/South Shingle Road Interchange (project 71333), US 50/Ponderosa Road Interchange - N. Shingle Road Realignment (project 71339) and Durock Road Widening - South Shingle Road to Robin Lane (project GP171).
|
| View On Microsoft Live Maps™
|
| Click image to view larger |
Click image to view larger |
 |
 |
| U.S. 50/Ponderosa Rd Interchange - Durock Rd Realignment (#71338) |
U.S. 50/Ponderosa Rd Interchange - Durock Rd Realignment (Aerial) |
| |
| Project Milestone Schedule |
Estimated Completion Date |
| PA&ED - Project Approval & Environmental Document |
December 2011 |
| PSE - Plans, Specifications & Estimates |
September 2013 |
| Advertise for Construction/Award Contract |
April 2013 |
| Construction Complete |
October 2015 |
|
| Total Estimated Project Cost:
$7,140,752
|
|
| |
| Project Status:
Currently being updated
Last Updated:
08/03/10 |
| |
| Project Contacts: |
| Project Manager: |
Jennifer Maxwell |
(530) 621-5900 |
Send Email |
| Deputy Director: |
Matt Smeltzer |
(530) 621-5900 |
Send Email |
|
| |
| Board of Supervisor District: | District 2, Supervisor:   Ray Nutting
|
|